BP Document Schedule 2nd Draft
Schedule of activities related to the BP document to be done before to publish the next Working Draft.
Status | Milestone/Activity | Target date(s) | What needs to be done | Contributors |
---|---|---|---|---|
working |
Develop and mature BPs content |
30 Mar 2015 |
Run over each BP and review |
|
working |
Community Feedback |
10 Apr 2015 |
Review and make possible changes on the document considering community feedback |
editors |
working |
Glossary |
23 Apr 2015 |
To have a revised version of the Glossary |
Yaso |
working |
Examples |
11 May 2015 |
To have examples in created scenarios to illustrate some BPs |
|
working |
Community Feedback |
11 May 2015 |
Consider all community feedbacks received until May 11 to the current set of updates |
|
Second Draft of DWBP Document |
18 May 2015 |
Freeze the document to be reviewed by the group before publishing it |
||
Second Draft of DWBP Document |
22 May 2015 |
Last feedback from the group before publishing it |
||
Second Draft of DWBP Document |
29 May 2015 |
Group voting the document |