Meeting minutes
Current testing progress
James: NVDA testing complete for alert
command button complete
Link complete
toggle button: 50% complete, intro meeting w/dillon tomorrow
Radio: complete.
This is all with prior version of NVDA; PAC is checking status w/latest version.
JAWS: Alert, command button and link. PAC has one run complete, Alysa WIP.
Toggle: 50% complete; Dillon will be doing the other 50%.
Radio: complete with 10 conflicts.
Isabel: Overview of conflicts includes unexpected behaviors where some are marked with other and some with overly verbose.
Next 3 plans for APG
Dialog, slider, and menubutton
Plan to update JAWS results for these three after the first 5 are published to APG.
APG support table updates
Preview of button example page:
https://
This is from APG pull request 2569
https://
Feedback captured in the APG pull request.
Scheduling work on remaining test plans
Coverage report: https://
Discussion of ow to build a schedule for the remaining test plans. There are 45 test plans total in the system. We have 8 in candidate review. We need to figure out a schedule for getting the remaining 37 in the candidate phase. Tentatively, we have 16 more that are nearly ready for candidate phase.
After we start publishing to APG, there will be a need to have a tentative and realistic schedule for when remaining example pages will have support tables.
James will start gathering information in a spreadsheet that we can use to determine approach to scheduling and prioritization.